Scaling Up Efficiency: District Energy at Penn State Harrisburg

A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Estudo de Caso Nº

174

Cliente

Penn State University – Harrisburg
USA

|

2021

Condições de Trabalho

Temperature: 98°C / 210°F | Pressure: 130 psi

Solução Pexgol

Pexgol 9″ & 14″

Aplicação

District Energy Network

Comprimento

Significant

Categorias

Scaling Up Efficiency: District Energy at Penn State Harrisburg

The Challenge

Penn State University Harrisburg required a reliable and efficient solution for its High-Temperature Hot Water Supply & Return (HT-HWS&R) system. The university needed a durable piping system capable of withstanding continuous high temperatures of 210°F at 130 psi while ensuring long-term performance with minimal maintenance. The solution had to be implemented underground, with direct burial, making resistance to environmental and operational stress a key requirement.

The project was executed in two phases, with Phase 1 completed in 2021 and an expansion (Phase 2) successfully implemented in 2023. With the growing infrastructure needs of the campus, further installations are anticipated in the future.

The Solution

For Phase 1 of the project, the university selected Pexgol 225 mm (9” Nom.) SDR 6 piping. The pipes were supplied in coils, allowing for efficient installation with minimal joints. The system was buried directly, with field-applied closed-cell spray foam insulation to ensure energy efficiency and temperature retention. Since its commissioning in 2021, the system has provided reliable service.

Following the success of Phase 1, Phase 2 was initiated in 2023, incorporating larger Pexgol 355mm (14” Nom.) and 225mm (9” Nom.) SDR 6 pipes. Like the first phase, the pipes were delivered in coils for direct burial, reducing installation time and costs while maintaining the same high-temperature and pressure resistance. The field-applied spray foam insulation continued to enhance thermal efficiency.

Penn State Harrisburg continues to expand its district energy network with Pexgol solutions, with additional phases expected in the near future. This project showcases Pexgol’s ability to meet demanding, long-term district heating requirements with efficiency, reliability, and cost-effectiveness.

Estudos de Caso Relacionados

Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Transforming water transportation with Pexgol technology

Pexgol’s Solution for CFE: A Leap in Durability and Efficiency

Comisión Federal de Electricidad
Mexico

 | 

2023
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021