Slurry Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Estudo de Caso Nº

40

Cliente

Sabinas Mine
Mexico

|

2017

Condições de Trabalho

Discharge by gravity, ambient temperature, abrasive fluid.

Solução Pexgol

Pexgol SDR 15 225 x 20.4.

Aplicação

Slurry transportation.

Comprimento

1642 meters.

Categorias

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client required to replace their current HDPE pipe lines where they transported slurry since they have frequent wear and leak issues on the joints. They used thermo-fusion welding, plus reinforcement with a Vitaulic 995 coupler. This sort of situation involved a considerable expense every time they failed, but they didn’t last long. The failures were every 3 to 4 months.

Pexgol Solution

In order to perform a better job when transporting slurry, the client decided to install a Pexgol pipe of 1642 meters SDR 15 225 x 20.4.

Thanks to Pexgol’s comprehensive piping solution, abrasion issues were avoided, since its cross-linked material is between 4 to 10 times more resistant than other pipes materials.

The pipes were supplied n sections up to 240 meters each one, consequently the installation was simple improving the process’s security and therefore protecting the environment.

Estudos de Caso Relacionados

Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020