Skip to content

Tailing Lines

Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Estudo de Caso Nº

63

Cliente

Ambatovy
Madagascar

|

2017

Condições de Trabalho

Pressure 800Kpa Slurry concentration of 35% solids Temperature 70°C to 80°C Composition (NH4) 2SO4 PH 6-8. Flow 3,200 m³/h (2.3 m/s)

Solução Pexgol

Pexgol 630 mm, Class 15

Aplicação

Slurry transportation

Comprimento

720 m

Categorias

Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

The Challenge

Ambatovy for it nickel mine has 15 km of tailing lines. The tailing distribution lines are made of DN700 carbon steel and this pipelines suffered from repetitive and frequent failures.
This failures were because of the effect of erosion, mainly due to the high liquid velocities inside the pipeline, especially in those areas where there is slack flow in the line.
To a lesser extent, further thinning of the pipeline wall occurs, due the presence of the highly corrosive ammonium sulphate salt (NH4)2SO4 . The frequent failures prompted the decision to replace the the carbon steel tailing pipeline with Pexgol pipes.

Pexgol Solution

After designing the lines in cooperation with Paterson & Cook, Ambatovy decided to install Pexgol 630 mm pipes on 2017.

The pipes were installed down hill from the pumping station where velocities are high. Testing the wall thickness periodically showed minimum effect of wear on the installed Pexgol pipes.

Another advantage that Ambatovy pointed out as a reason to use Pexgol systems is the simplicity of dismantling and reinstalling Pexgol pipes when raising the dam’s level, which saves time and money if comparing this to doing it with carbon steel pipes or carboon steel lined pipes.

Estudos de Caso Relacionados

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019