Skip to content

Transition to Corrosion-Free Diesel Delivery Systems

Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Estudo de Caso Nº

155

Cliente

Guaymas Protein
Mexico

|

2023

Condições de Trabalho

Temperature: 30°C / 86°F | Pressure: 5kg

Solução Pexgol

Pexgol 80 mm (3″), SDR 11

Aplicação

Diesel transport

Comprimento

100 m / 328 ft

Categorias

Transition to Corrosion-Free Diesel Delivery Systems

The Challenge

Guaymas Protein, a leader in fish-based protein products, faced significant issues with its existing carbon steel pipelines used for diesel transport. The prevalent saline environment in the area led to recurring corrosion of the pipes, resulting in frequent maintenance and replacements to prevent leaks and environmental contamination.

The Solution

By choosing Pexgol’s 3” RD 11 pipes, Guaymas Protein found an effective solution to its corrosion problems. Pexgol pipes, with their superior chemical and corrosion resistance, provided a durable alternative to carbon steel. The flanged coupling used in the installation facilitated a smooth transition, utilizing the existing supports on-site for a quick and simple setup. The lightweight and flexible nature of Pexgol pipes, along with their ability to be delivered in long lengths, significantly sped up the installation process and reduced the need for frequent maintenance, offering a sustainable and efficient system for diesel transportation.

Estudos de Caso Relacionados

Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020