Dry Gas Transportation

Dry Gas Line for Pump Activation.

Case Study Nº

104

Customer

ExxonMobil
Argentina

|

2020

Working Conditions

Maximum pressure: 9 kg / cm2 | Temperature: 25°C | Type of installation: underground

Pexgol Pipes

Pexgol 90 mm (3”) Class 10

Application

Dry gas transportation

Lenght

1880 m / 6168 ft

Categories

The Challenge

ExxonMobil, the unconventional oil field operator located in Neuquén (Argentina), was analyzing the installation of an underground line to convey dry gas. It was used as fuel to drive pumps to transport large volumes of water, used in the development of unconventional deposits.

The company evaluated different pipe alternatives such as: 2-inch diameter carbon steel, or Pexgol cross-linked polyethylene pipe. In addition to the cost, the main premise in the analysis was the reduction of the time of provision and installation of the pipe, which had to be in service in the shortest possible time to supply the needs of the drilling equipment operating in the deposit.

Pexgol Solution

The local team (Argpex) proposed to use a 90 mm diameter Pexgol pipe, class 10 in coils of just under 630 m each. The manufacture and transportation of 1000 km, was carried out in the course of a week.

The uncoiling and unwinding was carried out in a single day with minimal equipment consisting of an uncoiler and a vehicle to pull the pipe, in this case a backhoe. Electrofusion joints were made in one day.

The cost of the Pexgol material, including transportation to the location, represented less than 20% of the cost that a 2-inch carbon steel pipe would have consumed only materials and welding labor. A hydraulic test was carried out and the operation was subsequently started with positive results.

Related Case Studies

Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Transportation of brackish water to the main pumping station

Водопроводные линии — суровые природные условия

Работы на Мертвом море
Израиль

 | 

1993
Record-time intervention that avoided operational losses in a dehydration plant.

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Petróleos Sudamericanos
Argentina

 | 

2025
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
Дренаж воды из жесткой почвы

Отвод воды в карьере

Timmins Gold Corp Group, шахта Molimentales
Мексика

 | 

2016