Skip to content

Efficiency and Durability in Handling Muddy Water

Case Study: Pexgol’s Solution at the Palm Oil Plant.

Case Study Nº

163

Customer

Industrial Aceitera del Casanare
Colombia

|

2023

Working Conditions

Temperature: 90° a 100°C / 104°F | Flow: 40 m³/d | Fluid Components: Muddy water (POME) with a high organic load

Pexgol Pipes

Pexgol 200 mm, class 15

Application

Muddy Water Transport

Lenght

270 m / 885 ft

Categories

Efficiency and Durability in Handling Muddy Water

The Challenge

Industrial Aceitera del Casanare S.A., a palm oil processing plant in Colombia, faced the need to install a new line for the transportation of POME (Palm Oil Mill Effluent) from the plant to the oxidation ponds. This fluid, with a high organic load and operating at temperatures between 90°C and 100°C, posed a significant challenge due to its corrosive and abrasive nature. In 2022, the company had already tested a 100-meter section of Pexgol pipe, achieving excellent results in terms of resistance and durability.

The Solution

To address this challenge, Industrial Aceitera del Casanare decided to use 200 mm, class 15 Pexgol pipes over a length of 270 meters. The choice of Pexgol was based on its great resistance to high temperatures, corrosion, and abrasion, promising a durable and reliable solution for the transportation of POME. The implementation of Pexgol allowed the
plant to reduce downtime, as well as the costs and times associated with maintenance.

The installation of the 270 meters of Pexgol pipe was carried out efficiently using only two GP mechanical joints. This process did not require special tools, which further simplified the installation and minimized disruptions to plant operations. Since the implementation of the new line, Industrial Aceitera del Casanare has experienced a significant improvement in operational efficiency, with a notable reduction in maintenance times and plant downtime.

The success of this project highlights Pexgol’s ability to handle extreme operating conditions and highly corrosive and abrasive fluids.

Related Case Studies

Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Замена титановых труб на трубы Pexgol для транспортировки кислого раствора.

Обогатительный комбинат: транспортировка выщелоченной пульпы

Barrick Gold — Пуэбло Вьехо
Доминиканская Республика

 | 

2018
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023