Skip to content

Water Transportation on a Mining Road

Installation of Buried Pipes to Transport Water on a Mining Road.

Case Study Nº

79

Customer

CODELCO – Andina Mine
Chile

|

2019

Working Conditions

Extreme temperatures -20° to 35°C / -4° to 95°F

Pexgol Pipes

Pexgol 355 mm (14”), class 19

Application

Dewatering

Lenght

1700 m / 5577 ft

Categories

Installation of Buried Pipes to Transport Water on a Mining Road.

The Challenge

CODELCO required to transport water in an open pit mine section, destined for a pool located on the south side.

The job had to be done quickly to avoid damage to the access road. Therefore the pipeline should be located on the side of the road, buried.

Pexgol Solution

The client chose Pexgol because it was impossible to meet the delivery terms of the pipeline enabled with another type of pipe.
The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths and the possibility of burying it without the need for a sand enbeding. In addition, the pipeline was guaranteed to withstand strong temperature variations over the course of a year, ranging from -20°C to 35°C / -4°F to 95°F.

The installation was simple and fast. Crosspipe Systems carried out a complete induction to the pipe installation company, both in the uncoiling and in the welding of the couplings. In total 35 electrofusion couplings were made.

Related Case Studies

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010