Skip to content

Fish Discharge Lines

Installation of Pexgol Pipes to Transport Fish.

Case Study Nº

71

Customer

TASA
Peru

|

2018

Working Conditions

Extreme temperatures 5° to 21°C / 41° to 69.8°F

Pexgol Pipes

Pexgol 355 mm (14”), class 10

Application

Fish transport

Lenght

2100 m / 6900 ft

Categories

Installation of Pexgol Pipes to Transport Fish.

The Challenge

Tecnológica de Alimentos S.A. (TASA) required to transport Anchovy fish that measured between 12 and 15 cm from their vessels to the processing plant.

The fish was transported using HDPE pipes. The fish lost it mass due to rubbing against the walls of the pipes. These pipes were joined by thermofusion, which caused an internal burr (protruding portion of material) in the joints and increased damage to the fish. For this reason 450 mm HDPE pipes and a large amount of water must be used to transport the fish. The latter caused a considerable increase in the costs of water treatment.

Pexgol Solution

The client decided to replace its HDPE pipes and install 4 Pexgol lines for fish unloading in 3 plants of the company, with a length of 700 meters each and a diameter of 355 mm (14”) class 10. In the installation, concrete pieces were put on the pipe in order to make sure it doesn’t float on the sea.

Among the main advantages that were verified in this application were:

  • Smooth internal surface: Decreased mass loss, which results in the fish practically intact at the exit of the discharge, and therefore generates a better quality final product.
  • Lower costs for water treatment: It was possible to lower HDPE pipes of 450 mm PN 10 to Pexgol 355 mm (14”) class 10 pipes. Since it is a less rough pipe material, it allows the fish to be transported with less water, reducing more than 20% the cubic meters of water per linear meter.
  • Electrofusion unions: 178 unions were made that did not leave any type of internal burr (and therefore generate less damage to the fish).

Related Case Studies

Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013