Skip to content

Fast and Reliable Solution for Winemaking Processes

How Pexgol streamlined water transportation at Zuccardi Winery

Case Study Nº

172

Customer

Zuccardi Winery
Argentina

|

2024

Working Conditions

Temperature: Ambient | Flow rate: 150 L/min | Pressure: 2 bar | Fluid: Potable water

Pexgol Pipes

Pexgol 90 mm, class 15

Application

Potable water transport

Lenght

120 m / 393 ft

Categories

Fast and Reliable Solution for Winemaking Processes

The Challenge

Zuccardi Winery, internationally acclaimed for its innovation and quality in wine production, needed to implement a potable water transport line to supply both consumption and vinification processes. The challenge was to connect the storage tanks—located in a separate building—to the main plant through a system that ensured a fast, safe, and efficient installation. Additionally, the solution had to minimize leakage risks while optimizing installation time and costs.

The terrain conditions called for a reliable piping system that did not require a sand bed for burial and could be handled easily, considering operational and space constraints around the winery.

The Solution

Zuccardi selected 90 mm Pexgol class 15 pipes for the project. This decision was based on Pexgol’s key advantages, including:

  • Rapid Installation: The 120 meters of pipe were uncoiled and laid out in just 20 minutes.
  • Fewer Joints: Thanks to the long-length coil format, no joints were needed along the run, significantly reducing leakage risks and associated costs.
  • Easy Handling: The lightweight material enabled efficient transport and installation, even under limited operational conditions.
  • Strength and Adaptability: The pipe required no sand bed for burial, simplifying the installation process.

The final installation was carried out two days after trench preparation and took only 2 hours, including burial and backfilling. Both ends of the pipeline were connected using flanged couplings to ensure system integrity.

Related Case Studies

Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017