Slurry Transportation

Transport of acid slurry at high temperatures

Estudo de Caso Nº

12

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2012

Condições de Trabalho

Highly abrasive liquid at 80°C.

Solução Pexgol

Pexgol 335 mm, Class 10.

Aplicação

Discharge line.

Comprimento

350 m.

Categorias

Slurry Transportation

The Challenge

Moa Nickel required to transport highly abrasive liquid at high temperatures.

At the beginning they used fibre-reinforced plastic pipes, that later suffered damage caused by the abrasion. Furthermore, they used polypropylene pipes that didn’t work either, they couldn’t resist neither the abrasion nor the high temperatures.

The former pipes were short combined sections that required reinforced foundations and were very hard to install. The working periods were short because of the constant failures, furthermore, the maintenance cost was high as well.

Pexgol Solution

Once the client evaluated the operative conditions, they decided that Pexgol pipes were the best option, thanks to it abrasion resistance.

Additionally, special “U” pieces were developed for the client, made of steel with internal Pex lined.

After the installation, the Pexgol pipes operates perfectly till today, in excellent conditions and reducing head losses.

Estudos de Caso Relacionados

Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016
Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022