Skip to content

Abrasive Liquid Transportation

Acid liquor line with high levels of abrasion and sedimentation

Estudo de Caso Nº

21

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2014

Condições de Trabalho

70°C – 3 Bars.

Solução Pexgol

Pexgol 355 mm & Pexgol 315 mm, Class 12.

Aplicação

Acid liquor transportation with nickel, iron, cobalt and NaOH particles.

Comprimento

150 m.

Categorias

Acid liquor line with high levels of abrasion and sedimentation

The Challenge

Moa Nickel used rubber lined steel pipes to transport acid liquor.

Between 3 and 6 months they required to stop the plant for more than 24 hours, due to sedimentation issues that the steel pipe presented, reducing it inside diameter 60% less.

Furthermore, the steel pipe suffered leaks due to lined releases. Since the first moment that the liquid touched the steel, in a matter of minutes it was causing a leak.

Pexgol Solution

Golan provided Pexgol pipes of 355 mm and 315 mm with mechanical joints, and it only required to stop the plant one year after of the installation.

During that time, and due to the high sedimentation levels, the inside diameter was reduced just 30% less. The repair lasted only 4 hours, and it was done by hammer blows, in order to remove the material that

was obstructing the pipe. At the end, the pipe was functioning without problems.

Pexgol, it not only achieved to raise the production, but also the maintenance expenses were reduced. For every hour that the plant stopped, it cost hundreds of dollars to the company.

Estudos de Caso Relacionados

Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022