Groundwater Transportation

Groundwater Transportation With Ph Low Levels

Estudo de Caso Nº

29

Cliente

Grupo México, Buena Vista del Cobre Mine
Mexico

|

2015

Condições de Trabalho

Underground work (-250 m).

Solução Pexgol

Pexgol 90 mm (SDR 7.4).

Aplicação

Water transportation

Comprimento

200 m.

Categorias

Groundwater Transportation With Ph Low Levels

The Challenge

At “Buena Vista del Cobre” Mine the process water was extracted from deep wells. Formerly they worked with stainless steel pipes 316 with 9 months of operational lifetime that required to be replaced due to the corrosion, as a consequence of the low pH (between 1.5 and 2.5) from the groundwater.

Pexgol Solution

The client required a more flexible pipe, with longer operational lifetime than the steel, and minimize the stops at the plant. Therefore, a 3 inch Pexgol pipe was installed in one section, holding the weight of the pump, the cables, the water column and the pipe itself. The new pipe operational lifetime is 50 years.

The client received not only a durable pipe but also a complete solution including fittings for the pump and the discharge head. For a 3 inch 250 meter steel pipe, it would require more than 40 thread joints.

With Pexgol it only took 2 joints. This operation with a steel pipe it would cost $22.000 USD, when a Pexgol operation cost just a third of it. Plus the savings the client got from avoiding to stop the production for the failures.

Estudos de Caso Relacionados

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Comparison of brine transport

Albemarle Salar
Chile

 | 

2020
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Record-time intervention that avoided operational losses in a dehydration plant.

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Petróleos Sudamericanos
Argentina

 | 

2025
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014