Skip to content

Hot & Abrasive Potash Brine Processing

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Estudo de Caso Nº

87

Cliente

Fertilizer Company
Canada

|

2017

Condições de Trabalho

Temperature: 96°C / 204°F

Solução Pexgol

Pexgol 450 mm (18”), class 24 | Pexgol 400 mm (16”), class 15

Aplicação

Hot Ore and Brine Processing

Comprimento

400 m / 1312.34 ft

Categorias

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

The Challenge

A Canadian fertilizer company, and the largest producer of potash and the third largest producer of nitrogen fertilizer in the world, required to transport hot ore and brine in their facility in Saskatoon, Saskatchewan.

This was a new intake line. The facility traditionally used FRP and rubber-lined steel pipes. The FRP stress cracking issues and failure mechanism were a concern, and the client wanted to move away from it, but the conditions made material selection challenging.

The new line required to been able to transport saturated chloride brine at elevated temperatures with high resistance to abrasive slurries.

Pexgol Solution

The design of the line was carried out by the engineering company Wood Plc (then AMEC-FW) and Pexgol was selected. Pexgol went through several verification stages to ensure material suitability and verify design parameters:

  • Temperature and pressure suitability.
  • Abrasion resistance comparison with FRP, PP-RCT and other materials.
  • Expansion restraining forces analysis.
  • Support Distance Verification.

The system required a variety of nonstandards elbows, which were made by Golan’s Application Team.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

Estudos de Caso Relacionados

Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017