Transporting Brine at High Pressure

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Estudo de Caso Nº

100

Cliente

Mekorot
Israel

|

2020

Condições de Trabalho

Pressure: 36 bar | Flow rate: 120 m^3/hr | Chloride concentration: 10,100 mg/l

Solução Pexgol

Pexgol 250 mm (10”) Class 43

Aplicação

Brine transport at a Borehole

Comprimento

300 m / 984 ft

Categorias

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

The Challenge

Mekorot, the national water company of Israel and the country’s top agency for water management, required a corrosion resistant pipe that could hold very high pressure in a deep borehole (300 m). Furthermore, the pipe needed to be able to resist Chloride concentration of 10,100 mg/l.a

Pexgol Solution

A custom-made Pexgol pipe was installed (pipe 250 mm, class 43). The Pexgol pipe was provided in two coils of 150 m each. The two coils were connected by a special coupler that can hold the weight and the high pressure.

The other option that Mekorot considered was a pipe made of super duplex. Since installation of super duplex would take around 3 weeks and cost (approximately) 3,000,000 NIS ($9.3K) while installation of a Pexgol pipe is 3 days and cost about half. Pexgol pipe was the obvious choice.

Estudos de Caso Relacionados

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categorias:

Enhanced hydraulic and structural reliability for critical community infrastructure.

Optimization of Potable Water Supply for 1,600 residents

Rincón de la Candelaria
Mexico

 | 

2025