Transporting Brine at High Pressure

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Estudo de Caso Nº

100

Cliente

Mekorot
Israel

|

2020

Condições de Trabalho

Pressure: 36 bar | Flow rate: 120 m^3/hr | Chloride concentration: 10,100 mg/l

Solução Pexgol

Pexgol 250 mm (10”) Class 43

Aplicação

Brine transport at a Borehole

Comprimento

300 m / 984 ft

Categorias

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

The Challenge

Mekorot, the national water company of Israel and the country’s top agency for water management, required a corrosion resistant pipe that could hold very high pressure in a deep borehole (300 m). Furthermore, the pipe needed to be able to resist Chloride concentration of 10,100 mg/l.a

Pexgol Solution

A custom-made Pexgol pipe was installed (pipe 250 mm, class 43). The Pexgol pipe was provided in two coils of 150 m each. The two coils were connected by a special coupler that can hold the weight and the high pressure.

The other option that Mekorot considered was a pipe made of super duplex. Since installation of super duplex would take around 3 weeks and cost (approximately) 3,000,000 NIS ($9.3K) while installation of a Pexgol pipe is 3 days and cost about half. Pexgol pipe was the obvious choice.

Estudos de Caso Relacionados

Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018