High-pressure fluid transport

High-pressure water transport for the Southern Pit in a copper and zinc mine.

Estudo de Caso Nº

156

Cliente

Minera Antapaccay
Peru

|

2023

Condições de Trabalho

Exposed pipe with 30 bar (435 PSI) repump system

Solução Pexgol

Pexgol 355 mm (14”), class 30

Aplicação

Drain water transport

Comprimento

270 m / 885 ft

Categorias

High-pressure fluid transport

The Challenge

Minera Antapaccay faced the challenge of laying a pipeline over the slope of the Southern Pit from level 3870 to level 3632; for its project to drain groundwater from the bottom of the pit to connect to the water network for the plant, located in the mine area. Given the morphology of the slope in the terrain and the difference in heights (238 meters), a pipeline was required that would provide safety for working with high pressures and that could be exposed to the sun and low temperatures without the need to bury it.

The Solution

It was decided to install Pexgol since it is supplied in roll format, in this case up to 90 m in length. Compared to steel and HDPE, which are supplied in 12 or 14-meter sections, this supply format minimized labor and the likelihood of failure. Likewise, the potential for making joints on the slope’s body was reduced, decreasing the exposure of personnel to high-risk work. The laying was carried out using the brand’s equipment, making use of a pipe uncoiler, yellow line equipment, and manual pulling equipment (tirfor), due to the limited space for unrolling. Connections were made using electrofusion couplings and stub-ends.

Estudos de Caso Relacionados

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017