Skip to content

Backfill

Cement Slurry Injection to an Underground Mine

Estudo de Caso Nº

35

Cliente

Aguilar Mine
Argentina

|

2015

Condições de Trabalho

Fluids: Cement 450.2 g; Water 500 ml; Volume 670 cm.; Density 1.4 t/m. Pressure: Temporary pressures up to 33 k/cm2. Height difference: 300 meters.

Solução Pexgol

Pexgol 110 mm (4”) Class 24 (SDR 7.4).

Aplicação

Backfill

Comprimento

1,400 meters.

Categorias

Cement Slurry Injection To An Underground Mine

The Challenge

Due to this special circumstances, the client requested Pexgol pipes since they can be provided in 600 meters sections, they are flexible and highly resistant to abrasion and impacts.

The pipe sections were uncoiled hundreds of meters from the installation place, later they were descended with a hydraulic crane.

The end of the pipe was connected with a conical weight used as a guide to help it descend trough the robbins.

The ground was very harsh with sharp rocks, however the pipes were dragged, pulled and descended without problems.

The pipes were practically hanging from the surface of each level on the mine, supported by electro-fusion couplers. Despite the complicated conditions, the installation took only 60 net hours of work.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Estudos de Caso Relacionados

Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Water Supply & Fire Extinguisher Line

Cheddi Jagan International Airport
Guyana

 | 

2018