Skip to content

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Estudo de Caso Nº

183

Cliente

Vale
Brazil

|

2024

Condições de Trabalho

Temperature: 25–38 °C | Flow rate: 600 m³/h | Pressure: 18.5 bar | Fluid components: Water

Solução Pexgol

Pexgol PE-Xa Ø355 mm Class 30

Aplicação

Open-pit dewatering (pumping recovered water)

Comprimento

1,750 m (7 lines)

Categorias

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

The Challenge

With the depletion of the tailings dam at the Sossego mine, located in Canaã dos Carajás (Brazil), Vale needed to implement a new, reliable, and cost-effective pumping system capable of transporting recovered water back to the processing plant.\

The main challenge lay in the extremely demanding geographical conditions of the open-pit mine, with significant elevation differences and very rocky terrain.

Vale initially considered using conventional HDPE PE100 PN25 pipes. However, due to the excessive number of welds required, the system presented high risk, especially given the flow and pressure fluctuations within the mine.

This equipment posed additional operational hazards and demanded constant dismantling and relocation of pipe sections and supports by the personnel.

The total scope included more than 5,600 meters of piping, 466 unions, and a highly complex infrastructure with numerous electrofusion fittings and electrical controls. Vale required a more reliable, simple, resistant, and faster alternative—one capable of ensuring long-term operational continuity and minimizing shutdown times.

The Solution

Choosing Pexgol Ø355 mm Class 30 was a key decision for the project. Thanks to its unique mechanical properties—high flexibility, abrasion resistance, creep resistance, and durability under aggressive conditions—the pipe could fully withstand the demands of the new pumping system.

The redesign reduced the critical 250-meter section to 1,750 m of Pexgol pipe installed in seven independent lines, placed directly on rocky soil without the need for additional supports.

The new system includes:

  • 7 pumps of 542 HP each, operating with float switches.
  • 1,750 meters of Ø355 mm Pexgol pipe on 100 m and 50 m coils.
  • A fully automated system with frequency inverters and transformers for continuous operation.
  • ANSI Series 300 flanges, electrofusion saddles, and stiffening rings at each pump.
  • Local installation support from distributor local Rolcon, and weekly coordination with Vale, excavation, and operational teams.

Flexibility of Pexgol pipe minimized on-site unions thanks to long coil lengths, reducing welds and installation times, as well as significantly lowering potential failure points.

Results

 

DescriptionBefore (HDPE)After (Pexgol)
Total length5.600 m1.750 m
Welds46628
Floaters1757
Electrical centers21
Distribution network19 km12 km
Total platform weight130 tons61,5 tons
Booster system7 × 250 HPEliminated

Estudos de Caso Relacionados

Transforming water transportation with Pexgol technology

Pexgol’s Solution for CFE: A Leap in Durability and Efficiency

Comisión Federal de Electricidad
Mexico

 | 

2023
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018