Dewatering at an Open Cast Mine
Water Extraction From A Middle Pool To The Exterior Of The Mine
Estudo de Caso Nº
30
Cliente
Codelco, Ministro Hales Division
Chile
|
2016
Condições de Trabalho
Extreme temperatures (-25° to 40°C).
Solução Pexgol
Pexgol 160 mm Class 19 (SDR 9).
Aplicação
Water extraction
Comprimento
400 m.
Categorias

The Challenge
The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.
Pexgol Solution
A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.
Estudos de Caso Relacionados
Dewatering at an Open Cast Mine
Codelco, Ministro Hales Division
Chile
|
2016
Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport
Syncrude
Canada
|
2022
Drainage Lines in Underground Mine
Lundin Mining – Candelaria Norte Mine
Chile
|
2020
Implementation of Pexgol Pipelines for the Transport of Muddy Water
IACSA
Colombia
|
2023