Skip to content

Dewatering at an Open Cast Mine

Water Extraction From A Middle Pool To The Exterior Of The Mine

Estudo de Caso Nº

30

Cliente

Codelco, Ministro Hales Division
Chile

|

2016

Condições de Trabalho

Extreme temperatures (-25° to 40°C).

Solução Pexgol

Pexgol 160 mm Class 19 (SDR 9).

Aplicação

Water extraction

Comprimento

400 m.

Categorias

Water Extraction From A Middle Pool To The Exterior Of The Mine

The Challenge

The harsh environmental conditional where Codelco needed to install dewatering lines at the open cast mine, made the engineers opt for a change in their pipe material. They consider Pexgol as an option to decrease the repetitive failures they had with former materials.

Pexgol Solution

A 400 meters Pexgol pipe 160 mm Class 19 was provided, in one section without joints. The Pexgol pipe allowed a quick, reliable and easy installation on the harshest conditions of the open cast mine.

Estudos de Caso Relacionados

Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012

Categories:

Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021