Extraction of Underground Water

Extraction of underground water through wells

Estudo de Caso Nº

24

Cliente

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2010

Condições de Trabalho

Extreme environmental temperatures (-25°C to 40°C).

Solução Pexgol

Pexgol 280 mm, Class 10.

Aplicação

Underground water extraction.

Comprimento

200 m.

Categorias

Extraction of underground water through wells

The Challenge

Collahuasi Mine extracted process water through wells, they used a galvanized steel pipe. This pipe had several failures on its joints and demanded a long time installation process (around 3 days).

The client required a more flexible pipe, with longer working life than the steel, in order to keep the operations stable and minimized the stops in the plant for maintenance.

Pexgol Solution

A Pexgol pipe was installed in less than 3 hours, reducing 24 times the average installation time. Its weight was lighter than steel (70% less), so it involved less workers, less tolls, and less equipment to leave the well full operative. During the working life of the well, the Pexgol pipe didn’t require any sort of maintenance, and it was employed after in another application at the plant.

Estudos de Caso Relacionados

Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Greater operational efficiency with fewer joints and fast implementation.

Fresh Water Line Optimization in an Oil Field in Argentina

Phoenix Global Resources
Argentina

 | 

2025
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013