Skip to content

Mine Dewatering – High Pressure Conditions

Water line feed from wells to mine

Estudo de Caso Nº

6

Cliente

Antofagasta Minerals, Michilla Mine
Chile

|

2011

Condições de Trabalho

High pressure (over 24 bar).

Solução Pexgol

Pexgol 160×27, Class 30.

Aplicação

Dewatering.

Comprimento

700 meters.

Categorias

Mine Dewatering – High Pressure Conditions

The Challenge

Antofagasta Minerals faced constant water accumulation at the bottom of the mine, it was interfering with the extraction of the minerals. In addition, the mine operators faced:

  • High pressure (more than 24 bars) – resulting from the vertical height differences, which required a pipe that could withstand the pressure and be easily installed.
  • Pipe clogging in HDPE pipes – caused by scale formation on the pipe walls due to the presence of various salts, such as chlorides and sulfates, in varying concentrations in the water.
  • Long installation time – and the need to reduce it by installing a flexible, long pipeline with less connections.

Pexgol Solution

The installation of a Pexgol’s flexible pipe, which was produced and transported in coils, reducing both installation time as well as the number of joints. Since installation in early 2011, it has been working with no sign of clogging.

The client is fully satisfied with the pipe’s robust performance, including its quick, easy installation and ability to withstand pressures of higher than 24 bars.

Since Pexgol’s pipes require less maintenance than PE pipes and eliminate previous frequent failures, it will be used for many additional applications at the mine.

Estudos de Caso Relacionados

Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Work with High Pressures and Extreme Ambient Temperature

Water Transport in Copper Mine

Zaldivar SPA Mine
Chile

 | 

2018
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018