Skip to content

Mine Dewatering – High Pressure Conditions

Water line feed from wells to mine

Estudo de Caso Nº

6

Cliente

Antofagasta Minerals, Michilla Mine
Chile

|

2011

Condições de Trabalho

High pressure (over 24 bar).

Solução Pexgol

Pexgol 160×27, Class 30.

Aplicação

Dewatering.

Comprimento

700 meters.

Categorias

Mine Dewatering – High Pressure Conditions

The Challenge

Antofagasta Minerals faced constant water accumulation at the bottom of the mine, it was interfering with the extraction of the minerals. In addition, the mine operators faced:

  • High pressure (more than 24 bars) – resulting from the vertical height differences, which required a pipe that could withstand the pressure and be easily installed.
  • Pipe clogging in HDPE pipes – caused by scale formation on the pipe walls due to the presence of various salts, such as chlorides and sulfates, in varying concentrations in the water.
  • Long installation time – and the need to reduce it by installing a flexible, long pipeline with less connections.

Pexgol Solution

The installation of a Pexgol’s flexible pipe, which was produced and transported in coils, reducing both installation time as well as the number of joints. Since installation in early 2011, it has been working with no sign of clogging.

The client is fully satisfied with the pipe’s robust performance, including its quick, easy installation and ability to withstand pressures of higher than 24 bars.

Since Pexgol’s pipes require less maintenance than PE pipes and eliminate previous frequent failures, it will be used for many additional applications at the mine.

Estudos de Caso Relacionados

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023