Skip to content

Newmont’s Water Transportation Revolution with Pexgol Pipes

Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Estudo de Caso Nº

132

Cliente

Newmont Corporation
Argentina

|

2018

Condições de Trabalho

Soothills soil

Solução Pexgol

Pexgol 65, 75, 90, 110, 160, 200, 250 mm; classes 10, 12 & 15

Aplicação

Water transportation

Comprimento

5500 m / 18045 ft

Categorias

Newmont’s Water Transportation Revolution with Pexgol Pipes

The Challenge

Newmont Corporation, the world’s largest gold mining company, faced a significant challenge at its Cerro Negro unit in Santa Cruz, Argentina. The task at hand involved the transportation of water across challenging foothills terrain, a critical aspect of its mining operations. Given the demanding conditions, the ideal solution required pipes with superior durability, quality assurance for water installations, and agility for deployment and assembly. The initial plan involved over 300 joints, each representing a potential point of failure, and thus, a high risk to operational efficiency and reliability.

Pexgol Solution

Pexgol emerged as the most suitable solution for this task. Its range of pipes – Pexgol 63, 75, 90, 110, 160, 200, and 250 in classes 10, 12, and 15 – was chosen for their unmatched resilience, quality, and ease of installation. By supplying the pipes in rolls, several joints were eliminated from the pipeline, significantly reducing the risk of failure and decreasing installation time by 80% compared to other plastic pipes.

Pexgol’s permanent consultancy and training for the installers, coupled with its quick product availability, made it the perfect choice for Newmont Corporation. Additionally, Pexgol’s unique ability to avoid joints contributed to the ease, agility, and security of the pipeline, making cross-linked polyethylene (PEX) the most versatile and cost-effective solution for this project.

The installation process unfolded seamlessly. Newmont Corporation facilitated the uncolling of the Pexgol pipe coils, initially estimated to use 250 joints. The timeline for the installation was duly adhered to, with the entire pipeline spanning 5500 meters (approximately 18045 feet).

The utilization of Pexgol pipes effectively addressed Newmont Corporation’s water transportation needs, optimizing their gold mining operations’ efficiency, and contributing to its sustainable mining practices.

Estudos de Caso Relacionados

Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018