Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Estudo de Caso Nº

153

Cliente

Minera Fresnillo
Mexico

|

2021

Condições de Trabalho

Pressure: 130 psi (pump pressure) | Temperature: Ambient 35°C / 95°F | Fluid: Slurry (tailings), concentration 55%

Solução Pexgol

Pexgol 280 mm (12″), SDR 11

Aplicação

Tailings transportation

Comprimento

4800 m / 15748 ft

Categorias

Safety and durability: The heart of our solutions

The Challenge

Fresnillo, a leader in silver and gold production in Mexico, faced significant issues with its existing HDPE pipeline in its mining unit. Frequent failures in mechanical joints, including detachments of stub ends, failures in thermal fusions and flanges, created a potential risk of tailings spills, raising concerns for safety and environmental impact.

Pexgol Solution

Pexgol addressed this challenge with its scientifically proven and abrasion-resistant PE-X pipes, being up to four times more resistant than HDPE.

The electrofusion joints in Pexgol pipes ensured double safety, significantly reducing the risk of leaks. The installation was remarkably efficient, with each 120-meter roll laid out in just 20 minutes, allowing for rapid progress without compromising safety or quality.

A crucial aspect of Pexgol’s service was the comprehensive training provided to Fresnillo mine staff. This training ensured that the personnel were skilled in handling and installing Pexgol pipes, particularly mastering the electrofusion process. This skill development initiative not only facilitated smoother installations but also empowered the mine team with the knowledge and confidence to maintain pipeline integrity, reflecting Pexgol’s commitment to excellence and collaboration in every project.

Estudos de Caso Relacionados

Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015