Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Estudo de Caso Nº

176

Cliente

Buena Vista del Cobre
Mexico

|

2024

Condições de Trabalho

Temperature: Ambient (Design temp. 40°C) | Pressure: 160–180 psi | Flow Rate: 335 m³/hr | Fluid Composition: Molybdenite (MoS₂) in copper-molybdenum concentrate, with Mo, Cu, Fe, S, and Si

Solução Pexgol

Pexgol 8″ SDR 11

Aplicação

Molybdenum concentrate flotation

Comprimento

100 m / 328 ft

Categorias

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

The Challenge

At the Buena Vista del Cobre open-pit mine in Sonora, Mexico, molybdenum concentrate was transported through an HDPE pipeline. This system was regularly compromised by the highly scaling nature of the fluid, which consisted primarily of molybdenite (MoS₂) in a copper-molybdenum concentrate containing Mo, Cu, Fe, S, and Si.

The HDPE pipelines required daily manual intervention to prevent blockages, including frequent hammering along the line to maintain flow. Additionally, sections of the pipe had to be replaced at least once a month due to severe scaling buildup—resulting in high maintenance costs, operational delays, and recurring shutdowns.

The Solution

In 2024, the mine replaced 100 meters of 8” SDR 11 HDPE pipe with Pexgol pipe for its molybdenum concentrate flotation line. Pexgol was selected for its exceptional chemical and corrosion resistance, and especially its superior performance against scaling—a crucial feature given the aggressive nature of the transported slurry and the system’s operating conditions (160–180 psi pressure and temperatures up to 40°C).

The installation was fast and simple, requiring no specialized equipment. The Pexgol coil was unrolled using an excavator and front loader, and the pipe was laid in place within hours. Only electrofusion couplings (EF) were used, further simplifying the process.

Results

After one year of continuous operation, the client reported zero blockages and no maintenance required on the Pexgol line. This has eliminated the need for frequent replacements and cleaning, drastically reducing operational costs and ensuring uninterrupted flotation processes that meet Grupo México’s high efficiency standards.

Estudos de Caso Relacionados

Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022