Transport of Cyanide Water

Pexgol Pipe Installation for the Transport of Cyanide Water.

Estudo de Caso Nº

112

Cliente

Equinox Gold
Mexico

|

2022

Condições de Trabalho

Fluid: Neutralized Solution pH 10-12 – cyanide water | Flow: 1000m3/hr | Suction level: 1352 m3/hr | Discharge level: 1431/1432 m3/hr

Solução Pexgol

Pexgol 400 mm (16”), class 10 & 15

Aplicação

Transport of cyanide water

Comprimento

1475 m / 4839 ft

Categorias

Pexgol Pipe Installation for the Transport of Cyanide Water.

The Challenge

Equinox Gold, a Canadian mining company dedicated to gold extraction in different countries, required for its “Los Filos” mining unit to pump from the ADR plant a neutralized solution (cyaninated water) for evaporation through sprinklers. Previously, steel and HDPE pipes were used for this type of application.

The steel suffered from corrosion problems and the HDPE from crystallization, which generated problems in the thermofusions.

Pexgol Solution

It was decided to use Pexgol in sections of 12 meters with electrofusion connections. This way, possible corrosion problems were avoided and the costs of the project were reduced.

The installation was carried out by the same personnel working at the mine with training from the Pexgol technical team.

Estudos de Caso Relacionados

O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021