Skip to content

Underground Mine Dewatering

Installation Of Pexgol Hanging Pipes In Underground Mine

Estudo de Caso Nº

45

Cliente

Codelco Chuquicamata
Chile

|

2017

Condições de Trabalho

Extreme temperatures -10° to 40°C

Solução Pexgol

Pexgol 250 Class 19 (SDR 9)

Aplicação

Mine Dewatering

Comprimento

1400 meters

Categorias

Installation Of Pexgol Hanging Pipes In Underground Mine

The Challenge

The Chuquicamata mine needed to draw water at the lowest levels of the mine in order to keep it functioning. Commonly HDPE was used for this task, but the client this time required a fast and economical installation; two things that are not possible with this type of material.

Pexgol Solution

When this problem arose, the engineering company NBI (Grupo Astaldi), which was in charge of the project, decided to install Pexgol pipes to carry out the drainage.

The pipeline was connected with mechanical couplings to an existing HDPE pipe, which was then hung at 3 meters high with mining bolt supports.
The same activity carried out by HDPE pipes used sections of 12 meters, with mechanical couplings joints, which have greater potential for faults in the line. Thanks to the flexibility and capacity of the Pexgol pipes to be delivered in long stretches, the installation took considerably less time.

PEXGOL VS HDPE PIPELINE PERFORMANCE SUMMARY BY NBI

Pexgol pipe installation performance (200 meter sections):

UnitsQuantityTime (h)Effective Time (h)
Positioning
(from the floor to the support)
m2001616
Alignment (15° slope)m20055
Connections (between pipes)un277
Jointsun277
Total Hours3535
Total Days1.53

 

Performance of HDPE pipe installation (12 meter sections) with Victaulic joints:

UnitsQuantityTime (h)Effective Time (h)
Positioning
(from the floor to the support)
m1222
Alignment (15° slope)m1222
Connections (between pipes)un266
Jointsun244
Total Hours (12 m)1414
Total Hours (200 m)238238
Total Days(200 m)1020

 

Differential Pexgol vs HDPE pipes by NBI

  • The assembly performance of Pexgol pipe is at least 7 times higher than HDPE in operations inside an underground mine.
  • The pipe can be dragged (2 to 5 km) into the mine without suffering any damage.
  • The flexibility of the Pexgol pipe, allows the assembly in the walls of the tunnel, 3 meters above ground level. It is much easier and faster, because it can adapt to the irregularities of an underground mine.
  • Pexgol possesses greater operational reliability when reducing connections.

Uncoiling Process:

Installation:

Estudos de Caso Relacionados

Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017