Vertical Dewatering

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Estudo de Caso Nº

69

Cliente

Ferrexpo Poltava Mining
Ukraine

|

2019

Condições de Trabalho

Vertical installation | Ambient temperature: -30°C to 40°C / -22°F to 104°F

Solução Pexgol

Pexgol 315 mm (12”), class 30 | Pexgol 315 mm (12”), class 24 | Pexgol 315 mm (12”), class 19 | Pexgol 280 mm (10”), class 10

Aplicação

Mine Dewatering

Comprimento

2700 m

Categorias

Installation of Pexgol Pipes for Drainage in a Vertical Ground

The Challenge

Ferrexpo Poltava Mining required the installation of pipeline for mine dewatering to be installed vertically from the bottom of the quarry to its surface. The pipe needed to be resistant to cracks and be provided in long sections in order to avoid many joints.

Pexgol Solution

The client decided to install Pexgol pipes with OD 315 mm (12”) with 30, 24 and 19 class in coils by 90 and 120 m each for most difficult areas where the pressure varied from 32 to 15 bars. At the end of the line Pexgol OD 280 mm (10”), class 10 pipes were used in straight sections of 11.8 m.
All the pipes were connected by electrofusion couplers. In the places with high pressure were also used reinforcements for a safe installation.

A Caterpillar D10T bulldozer and the 40 ton excavator was used for unwinding the coils on core. Then the pipe were dropped from the top by the bulldozer & excavator. All connections were made with the electrofusion couplers. In the most difficult areas were also used reinforcements and fixpoint bridges.

Estudos de Caso Relacionados

Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015