Skip to content

Water Lines – High Pressure Water Feed Lines

Water line feed from wells to mine

Estudo de Caso Nº

5

Cliente

Yamana Gold, Meridian Mine
Chile

|

2012

Condições de Trabalho

High pressure (over 24 bar), corrosion and ambient temperature at 40°C/104°F. The first 2,750 meters of pipes were covered in sand, the last 2,750 meters were exposed to the sun.

Solução Pexgol

Pexgol 225×30.8, Class 24.

Aplicação

Dewatering.

Comprimento

5,500 meters.

Categorias

Water Lines – High Pressure Water Feed Lines

The Challenge

The high pressure and corrosion caused constant failure of the two initial parallel steel pipelines and serious threats to the production process.

One steel pipeline was out of service for at least two years and the other suffered from severe corrosion. Since this was the only main line transporting water to the production line, it was critical for the whole production process. The client required a highly durable and a quick install solution for non-stop performance

Pexgol Solution

The replacement of the steel pipeline with Pexgol’s flexible and high resistance to corrosion pipe solution eliminated previous failures. In addition, Pexgol supplied easy-to-install longer pipes.

The client is so pleased with the solution that he will be replacing the HDPE pipes that are part of this line as well.

Estudos de Caso Relacionados

Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023