Water Transportation on a Mining Road

Installation of Buried Pipes to Transport Water on a Mining Road.

Estudo de Caso Nº

79

Cliente

CODELCO – Andina Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -20° to 35°C / -4° to 95°F

Solução Pexgol

Pexgol 355 mm (14”), class 19

Aplicação

Dewatering

Comprimento

1700 m / 5577 ft

Categorias

Installation of Buried Pipes to Transport Water on a Mining Road.

The Challenge

CODELCO required to transport water in an open pit mine section, destined for a pool located on the south side.

The job had to be done quickly to avoid damage to the access road. Therefore the pipeline should be located on the side of the road, buried.

Pexgol Solution

The client chose Pexgol because it was impossible to meet the delivery terms of the pipeline enabled with another type of pipe.
The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths and the possibility of burying it without the need for a sand enbeding. In addition, the pipeline was guaranteed to withstand strong temperature variations over the course of a year, ranging from -20°C to 35°C / -4°F to 95°F.

The installation was simple and fast. Crosspipe Systems carried out a complete induction to the pipe installation company, both in the uncoiling and in the welding of the couplings. In total 35 electrofusion couplings were made.

Estudos de Caso Relacionados

Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020