Recovered Water Transportation
Grey Water Transportation
Estudo de Caso Nº
38
Cliente
Coeur Mexicana S.A. de C.V. Palmarejo
Mexico
|
2017
Condições de Trabalho
74 psi, altitude dierence= 34 m, Au= 0.12 ppm, Ag= 0.18 ppm, Cu= 1.13 ppm, Fe= 0.73 ppm, Cn total= 1.5 ppm, Ca= 458 mg/dL, Ph= 8
Solução Pexgol
Pexgol SDR 15 225 x 20.4.
Aplicação
Water transportation.
Comprimento
1200 meters.
Categorias

The Challenge
Coeur Mexicana required to transport recovered water, but they wanted to conduct an installation in the minimum time possible that won’t require contractors, specialized personnel neither expensive equipment.
Pexgol Solution
The client decided to install Pexgol, due to it quick and easy installation, that if was carried out with steel or HDPE pipes, it would require 100 joints. But, since it was done with Pexgol pipes it only took 4 joints.
Furthermore, it was considered the security that Pexgol pipes offer, since it’s supplied in long length coils, which reduces leakages.
Pexgol’s team advised the client during the whole process from the design to the installation.
Estudos de Caso Relacionados
Hot Water Distribution for Solar Technology
Raygen
Australia
|
2021
Groundwater Transportation
Grupo México, Buena Vista del Cobre Mine
Mexico
|
2015
Greater Efficiency and Safety in Leaching with Pexgol Pipes
Barrick Gold Corp.
Argentina
|
2025
Innovation in Safety: Pexgol Piping System for LPG Supply
Rawabi City
Israel
|
2010
From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool
Gordon Pool
Israel
|
2023