Skip to content

Comparison of brine transport

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Estudo de Caso Nº

75

Cliente

Albemarle Salar
Chile

|

2020

Condições de Trabalho

Flow: 120 m3/h

Solução Pexgol

Pexgol 200 mm (8”), class 10

Aplicação

Brine transport

Comprimento

112 m / 367.45 ft

Categorias

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

The Challenge

Albemarle salar decided to conduct a comparative test on their brine pipelines. The objective was to test the high resistance to scale formation that Pexgol pipes possess compared to conventional high-density polyethylene (HDPE) pipes.

Pexgol Solution

A Pexgol pipe was uncoiled by the main road from the salar to the parapet of 13D well, finally placing the pipe in the direction of 14D well to start the assembly according to its final disposition.

The flexibility of the Pexgol pipe allowed to fit easily into the layout, and its ability to be dragged greatly favored installation time.
Thanks to its high mechanical and impact resistance, Pexgol does not require the use of a special jacket.

For connection to the pump, a flanged coupling was used: clamp-type mechanical accessory with flange adjustment.

Pipe TypePexgol Cost vs OthersPexgol Total Investment Costs vs Others
Rubbed steel A53 Gr, B Sch. 201:1.41:2
Stainless steel 316L, Sch. 201:21:3
Titanium B862, Gr.2, 3 mm thk1:2.31:3.2
Polypropylene PP-H, SDR 171:3.81:4.2

 

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Sedimentation comparison: HDPE pipe after 30 days of use.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Sedimentation comparison: Pexgol pipe after 60 days of use.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
After 30 days of operation, the HDPE pipe has incrustations with an approximate thickness of 50 mm.
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.
Cleaning HDPE pipes presents a great physical wear and tear for operators, as they must hit hard to loosen the scale, which means more hours spent on maintenance.

Estudos de Caso Relacionados

Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Free Chlorine Potable Water Supply

Rabin Medical Center
Israel

 | 

2020
Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024