Water Transportation on a Mining Road

Installation of Buried Pipes to Transport Water on a Mining Road.

Estudo de Caso Nº

79

Cliente

CODELCO – Andina Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -20° to 35°C / -4° to 95°F

Solução Pexgol

Pexgol 355 mm (14”), class 19

Aplicação

Dewatering

Comprimento

1700 m / 5577 ft

Categorias

Installation of Buried Pipes to Transport Water on a Mining Road.

The Challenge

CODELCO required to transport water in an open pit mine section, destined for a pool located on the south side.

The job had to be done quickly to avoid damage to the access road. Therefore the pipeline should be located on the side of the road, buried.

Pexgol Solution

The client chose Pexgol because it was impossible to meet the delivery terms of the pipeline enabled with another type of pipe.
The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths and the possibility of burying it without the need for a sand enbeding. In addition, the pipeline was guaranteed to withstand strong temperature variations over the course of a year, ranging from -20°C to 35°C / -4°F to 95°F.

The installation was simple and fast. Crosspipe Systems carried out a complete induction to the pipe installation company, both in the uncoiling and in the welding of the couplings. In total 35 electrofusion couplings were made.

Estudos de Caso Relacionados

The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Comparison of brine transport

Albemarle Salar
Chile

 | 

2020
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019