Free Chlorine Potable Water Supply

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Estudo de Caso Nº

94

Cliente

Rabin Medical Center
Israel

|

2020

Condições de Trabalho

Temperature: 4° to 85°C | Pressure: 6 bar

Solução Pexgol

Pexgol CL+ 16 mm – 75 mm class 24

Aplicação

Free Chlorine Potable Water Supply

Comprimento

1000 m

Categorias

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

The Challenge

As one of the most major and central medical institutions in Israel, “Rabin Medical Center” must meet the most severe international health standards. Free Chlorine, if used to sterilize a potable water supply, may lead to Chlorine corrosion, and could even rupture pipes and infrastructure. As little as 0.3 ppm of Chlorine in the water system will lead to high wear and degradation and necessitate frequent replacements.

Pexgol Solution

Pexgol CL+ has proven durability to free Chlorine in a concentration between 0.3-0.5 ppm and working pressures up to 6 bar. By installing Pexgol CL+ in a potable water system, “Rabin Medical Center” can continue to insure a clean and safe supply of water to the hospital.

Estudos de Caso Relacionados

Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Transportation of River Water in Rough Terrain

Water Transport in Complex Terrain

Southern Copper Corporation
Peru

 | 

2019
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017