Recovered Water Transportation

Grey Water Transportation

Estudo de Caso Nº

38

Cliente

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

|

2017

Condições de Trabalho

74 psi, altitude dierence= 34 m, Au= 0.12 ppm, Ag= 0.18 ppm, Cu= 1.13 ppm, Fe= 0.73 ppm, Cn total= 1.5 ppm, Ca= 458 mg/dL, Ph= 8

Solução Pexgol

Pexgol SDR 15 225 x 20.4.

Aplicação

Water transportation.

Comprimento

1200 meters.

Categorias

Grey Water Transportation

The Challenge

Coeur Mexicana required to transport recovered water, but they wanted to conduct an installation in the minimum time possible that won’t require contractors, specialized personnel neither expensive equipment.

Pexgol Solution

The client decided to install Pexgol, due to it quick and easy installation, that if was carried out with steel or HDPE pipes, it would require 100 joints. But, since it was done with Pexgol pipes it only took 4 joints.

Furthermore, it was considered the security that Pexgol pipes offer, since it’s supplied in long length coils, which reduces leakages.

Pexgol’s team advised the client during the whole process from the design to the installation.

Estudos de Caso Relacionados

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016