Replacement of Metal Pipe with PE-X for Formation Water

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Estudo de Caso Nº

116

Cliente

Enap Sipetrol Ecuador
Ecuador

|

2022

Condições de Trabalho

Pressure: 25 psi | Temperature: 71°C / 160°F

Solução Pexgol

Pexgol 225 (8″), Class 24

Aplicação

Formation water transport

Comprimento

160 m / 525 ft

Categorias

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

The Challenge

Enap Sipetrol Ecuador, is a branch of the Chilean state oil company Enap.

At their plant, they needed to transport formation water with 65,000-70,000 ppm of sodium chloride, which also had high salinity. This formation water has its origin at the outlet of a three-phase separator, up to a water storage tank. The existing metal pipes in the local market that are used for these processes corrode quickly and present leaks along the way. This situation made it necessary to apply chemical treatment to the pipes, with the cost that this represented, and even so, the treatment did not guarantee the integrity of the pipe.

Pexgol Solution

It was decided to use Pexgol pipe due to the working conditions that it can withstand for these applications and that also has a longer lifespan than the metal pipes usually installed, after the tests carried out, it was satisfactorily observed that it has not been any inconvenience, there are no leaks, no presence of corrosion and no solids adhered.

The installation of the 160 m of 225 mm diameter pipe was carried out with the collaboration of 12 people due to its dimensions and weight, in addition, locally manufactured “cradle” type supports were placed. For the assembly of the pipe, a horizontal unwinding machine was used, a crane truck, mobile roller stations for displacement, mechanical keys, torque meter and manual tools, 4 flanged couplings were installed for the terminations with their respective fixing clamps since that line it was installed in 2 sections.

Estudos de Caso Relacionados

Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020