Skip to content

Transportation of sodium sulfide

Pvc Pipe Replacement by Pexgol

Estudo de Caso Nº

44

Cliente

Magnelec S.A. de C.V.
Mexico

|

2018

Condições de Trabalho

Pressure 60 psi; Temperature 60° to 80°C; Highly Corrosive Liquid

Solução Pexgol

Pexgol 225×20.4 SDR 15

Aplicação

Sodium Sulfide Transportation

Comprimento

600 meters

Categorias

Pvc Pipe Replacement by Pexgol

The Challenge

Magnelec had installed a Yellomine pipe (PVC pressure pipe) where it was transporting sodium sulfide.
Due to changes in temperature in the fluid, dilatation and contraction of the pipe was frequent issue. The pipe was installed in sections of 6 metersc each, generating leaks in the joints, which caused a lot of losses in the line of conduction. Also, there were problems in the stainless steel pipes with leaks in the joints of the welds.

Pexgol Solution

Due to this frequent problems, Magnelec decided to replace its pipes with Pexgol. Once the Yellomine pipes were replaced by Pexgol pipes, the problem of leakage was solved, thanks to the fact that Pexgol pipes were supplied in rolls of great lengths, which decreased the number of joints. The material of Pexgol pipes is flexible and absorbs the movements that can be generated by changes in temperature.
They are also highly resistant to corrosion and to high and low temperatures, so it was the ideal solution.
The installation was quick and easy in sections of 200 meters in length with mechanical GP connections. The installation took around 7 days. The tools used were tightening wrenches, slings, crane, etc.

Estudos de Caso Relacionados

Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Transport Of Palm Oil Slurry At 95°C.

Transport of Palm Oil Slurry

Loma Fresca
Colombia

 | 

2017
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020