Water Transport for Fire Network

Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Estudo de Caso Nº

117

Cliente

Profertil
Argentina

|

2022

Condições de Trabalho

Pressure: 15 bars | Temperature: Ambient

Solução Pexgol

Pexgol 180 (6″), 225 (8″) & 280 (12″) mm, Class 15

Aplicação

Water transport for fire network

Comprimento

1000 m / 3280 ft

Categorias

Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

The Challenge

Profertil, an Argentine company specializing in the manufacture of fertilizers, has a fire network that is more than 10 years old working with carbon steel pipes.

Given that the water they transport has a high chloride content, the lines were affected by corrosion and in many cases even with scale that obstructed the pipe by 50%.

Pexgol Solution

In order to have an efficient fire-fighting network, the Profertil project team opted for a plastic pipe that does not suffer from corrosion, with less possibility of incrustations and its installation does not require specialized machinery.

Likewise, given bad experiences with other types of pipes in relation to installation and operation, the maintenance team carried out pressure tests and resistance to external damage with a sample that was delivered to them.

Finally, 3 lines with Pexgol pipes were installed and it is scheduled in other stages to completely replace the fire network, a total estimate of 7 km.

Electrofusion joints and accessories were used to carry out the derivations and changes of direction.
In relation to other materials and considering that in several places where the pipe had to be buried, obstacles were found from cables and other pipes, the installation was successful.

Estudos de Caso Relacionados

Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Replacement of a HDPE Pipe for a Pexgol Pipe

Compressed Air Transportation

Saucito S.A. de C.V. Mine
Mexico

 | 

2017