2,900 Meters of Pexgol Installed and Pressure-Tested in Just 3 Days

Pexgol reduced the number of joints, accelerated installation, and improved network reliability.

Estudo de Caso Nº

195

Cliente

Petróleos Sudamericanos
Argentina

|

2026

Condições de Trabalho

Operating pressure: 6 kg/cm² / 85 psi | Temperature: 30°C / 86°F | Flow rate: 40,000 m³/day | Transported material: Treated methane gas, 100% dry

Solução Pexgol

Pexgol 110 mm, Class 10

Aplicação

Dry gas / treated methane transportation

Comprimento

2,900 m / 9,514 ft

Categorias

2,900 Meters of Pexgol Installed and Pressure-Tested in Just 3 Days

The Challenge

Petróleos Sudamericanos S.A., an energy company with more than 30 years of experience in oil and gas exploration and production, needed to replace an existing dry gas transportation pipeline in Catriel, Río Negro, Argentina.

The previous carbon steel pipeline had been in service for many years and was showing signs of corrosion and wear. To ensure operational continuity and improve system reliability, the client required an alternative capable of transporting treated methane gas, 100% dry, under operating conditions of 6 kg/cm² pressure, a temperature of 30°C / 86°F, and a flow rate of 40,000 m³/day.

In addition to material resistance, the project required an efficient installation process with fewer joints and shorter field execution times.

The Solution

For this project, 2,900 m / 9,514 ft of 110 mm, Class 10 Pexgol pipe were installed for dry gas transportation.

Thanks to its flexibility, low weight, and availability in long sections, Pexgol made it possible to complete the installation and pneumatic pressure test in just three days. Only six joints were required along the entire 2.9 km / 1.8 mi pipeline, significantly reducing critical points and improving network safety.

Pexgol’s corrosion resistance, ease of handling, and long service life made it an ideal solution for replacing the existing metallic pipeline.

This was the contractor’s second project using Pexgol. After gaining experience with the material during the first installation, the contractor selected Pexgol again due to its ease of installation and operational advantages over traditional piping solutions.

Estudos de Caso Relacionados

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
A solution designed to operate safely and reliably under high temperatures and demanding installation conditions.

A Flexible Solution for Formation Water UnderDemanding Conditions

Pluspetrol
Argentina

 | 

2026
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018
Pexgol reduced the number of joints, accelerated installation, and improved network reliability.

2,900 Meters of Pexgol Installed and Pressure-Tested in Just 3 Days

Petróleos Sudamericanos
Argentina

 | 

2026