High Pressure Water Transport

High Pressure Water Transport for a Gold Mine.

Estudo de Caso Nº

86

Cliente

Mansfield Mine
Argentina

|

2019

Condições de Trabalho

Exposed pipe with repump systems at 21 bar (305 PSI)

Solução Pexgol

Pexgol 225 mm (8″), class 24, 19, 15 & 12

Aplicação

Water transport

Comprimento

12.5 km

Categorias

High Pressure Water Transport for a Gold Mine.

The Challenge

The engineering company SAXUM had the challenge of designing the main water supply line for Mansfield’s “Lindero Gold Mine” project, which through heap leaching removes and processes mineral.

Given the differences in height (more than 300 meters in total) and the length, a pipe was required that would provide safety to work with high pressures and that can be exposed to the sun without the need to bury it.

Due to the climatic conditions of the area, with low temperatures and strong winds, added to the height (above 4000 m above sea level), a simple and quick solution to install was sought, since otherwise the costs of assembly would be very high.

Pexgol Solution

It was decided to install Pexgol since it is supplied in coils, in this case up to 280 meters in length. Compared to steel and HDPE supplied in 12 or 14 meter lengths, this supply format kept labor and the posibility of failure to a minimum.

Approximately 1,400 meters were installed per day with only three operators and a backhoe. The connections were made by electrofusion couplings.

Estudos de Caso Relacionados

Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Work with High Pressures and Extreme Ambient Temperature

Water Transport in Copper Mine

Zaldivar SPA Mine
Chile

 | 

2018
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018