Open Cast Mine Dewatering

Dewatering without Supports

Estudo de Caso Nº

37

Cliente

El Volcan Mine Arcelor Mittal
Mexico

|

2017

Condições de Trabalho

Pressure 189 psi; height difference 130 m; solids 15-20 %; fluid temperature 20-25°C.

Solução Pexgol

Pexgol Class 15 160 x 14.6.

Aplicação

Dewatering

Comprimento

650 meters.

Categorias

Dewatering without Supports

The Challenge

El Volcan Mine was facing a excess water that required dewatering. During rainy season the Mine area suffers from constant floods due to high level groundwater that wasn’t taken under consideration.

In addition, the client was looking for a quick and easy to install solution, since the pipe was going to be suspended, and a regular pipe will require supports.

Pexgol Solution

El Volcan Mine decided to replace their current 6” RD11 HDPE pipe for a Pexgol class 15 pipe 160 x 14.6 due to it quick and easy installation.

650 meters of Pexgol pipe was provided. The installation was done in a quick and efficient way, and count with Pexgol technical support during the whole process.

Estudos de Caso Relacionados

Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015