Transportation of Ore Slurry

Replacing steel pipes suffering from sediment formation

Estudo de Caso Nº

10

Cliente

RUSAL, aluminum factory
Russia

|

2012

Condições de Trabalho

Specific gravity was 1.510-1.550 kg/l, pressure 2 Bar (maximum 3-4 Bar), temperature of 99°C. Chemical composition: Na2O, AI2O3, F32O3, SiO2, CaO. Flow rate: 180M3/H.

Solução Pexgol

160 mm class 15 (SDR 11).

Aplicação

Industrial.

Comprimento

15 meters with flared ends

Categorias

Transportation of Ore Slurry

The Challenge

The main challenges were corrosion and scaling formation on the inner surface of existing steel pipes, causing a decrease of inner diameter of the pipes and consequent decrease of their throughput ability.

Pexgol Solution

Replacement of the existing 159 mm steel pipe with a 160 mm class 15 (SDR 11) Pexgol pipe.

The test line consists of three parts: One section is a white G-Pex pipe manufactured in Moscow, approximately 12 m long. Two more sections are 0.5 m long, each of black Pexgol pipe with flared ends, manufactured in Golan Plastic Products, Israel. These sections were connected by Plasson’s

Electro-fusion Pex-2-Pex couplers. During the entire operation the pipe was under continuous vibration because of a grinder operation.

The pipe was installed by the field team of Polimerteplo Group Llc accompanied by the field installation engineer of Gloan Plastic Products Ltd.

Estudos de Caso Relacionados

Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024