Transportation of Ore Slurry

Replacing steel pipes suffering from sediment formation

Estudo de Caso Nº

10

Cliente

RUSAL, aluminum factory
Russia

|

2012

Condições de Trabalho

Specific gravity was 1.510-1.550 kg/l, pressure 2 Bar (maximum 3-4 Bar), temperature of 99°C. Chemical composition: Na2O, AI2O3, F32O3, SiO2, CaO. Flow rate: 180M3/H.

Solução Pexgol

160 mm class 15 (SDR 11).

Aplicação

Industrial.

Comprimento

15 meters with flared ends

Categorias

Transportation of Ore Slurry

The Challenge

The main challenges were corrosion and scaling formation on the inner surface of existing steel pipes, causing a decrease of inner diameter of the pipes and consequent decrease of their throughput ability.

Pexgol Solution

Replacement of the existing 159 mm steel pipe with a 160 mm class 15 (SDR 11) Pexgol pipe.

The test line consists of three parts: One section is a white G-Pex pipe manufactured in Moscow, approximately 12 m long. Two more sections are 0.5 m long, each of black Pexgol pipe with flared ends, manufactured in Golan Plastic Products, Israel. These sections were connected by Plasson’s

Electro-fusion Pex-2-Pex couplers. During the entire operation the pipe was under continuous vibration because of a grinder operation.

The pipe was installed by the field team of Polimerteplo Group Llc accompanied by the field installation engineer of Gloan Plastic Products Ltd.

Estudos de Caso Relacionados

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013