Water Transport in Copper Mine

Work with High Pressures and Extreme Ambient Temperature

Estudo de Caso Nº

68

Cliente

Zaldivar SPA Mine
Chile

|

2018

Condições de Trabalho

Pressure: 24 & 30 bar | Ambient temperature: 5° to 28°C / 41° to 82°F

Solução Pexgol

Pexgol 160 mm (6”), Class 15 | Pexgol 160 mm (6”), Class 19 | Pexgol 160 mm (6”), Class 24 | Pexgol 160 mm (6”), Class 30

Aplicação

Water transport

Comprimento

9500 m

Categorias

Work with High Pressures and Extreme Ambient Temperature

The Challenge

The mining company Zaldivar SPA (Barrick) needed to implement a line of drinking water from the storage pond to the camp sector, crossing the entire mining site. Two thirds of the layout required a pressure of 24 and 30 bar, using the minimum amount of joints possible and in the shortest time conceivable.

Pexgol Solution

It was decided to install 9500 m of Pexgol pipe due to its advantages:

  • High pressure resistance (24 and 30 bar)
  • Supply in long lengths (sections of up to 600 meters) minimizing assembly time and number of joints.
  • Resistance to mechanical stresses due to pipe dragging in hard to reach areas.

The installation was simple, fast and safe. Without resources or special tools, shortening the known assembly program with HDPE pipes.

Estudos de Caso Relacionados

Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024
Replacement of Carbon Steel Pipe for a Pexgol Pipe

Water Transportation

Cargill
Mexico

 | 

2017
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013